Construction Management Practice Exam 2025 - Free Construction Management Practice Questions and Study Guide

Question: 1 / 400

What is a punch list?

A stencil for punching holes in steel

A form used for logging machine hours worked

Items that must be completed prior to contract completion

A punch list is an essential document in construction management that details specific items that must be completed or corrected before the contract can be considered finished. This list is typically created towards the end of a project, often during the final inspection, to ensure that all aspects of the work meet the requirements set forth in the contract. It usually includes tasks like fixing defects, completing certain installations, or addressing any items that do not conform to the project specifications. The completion of items on the punch list is crucial for finalizing the project and is often tied to the release of the final payment to the contractor.

The other options provided do not accurately represent the concept of a punch list. A stencil for punching holes in steel, for instance, relates to a manufacturing or fabrication process rather than project completion. Logging machine hours pertains to equipment usage tracking and is a different aspect of project management. Lastly, while collecting accurate field information is important for contract status reports, it does not specifically address the final checks and tasks before a project is completed, which is the essence of a punch list.

Get further explanation with Examzify DeepDiveBeta

A system for collecting accurate field information for a contract status report

Next Question

Report this question